7 elevators have been installed at Twin Tower project

7 elevators have been installed at Twin Tower project

26 Nov 2018

ICE has finished installation of 7 elevators on A1 block of Twin Tower project. 54-floor 6 passenger and 1 service elevators have already run operation

"I can definitely say that the elevators are installed ideally and we could manage it according to contract terms. The purchaser is satisfied and that's the most important issue for us. Process of another 7 units installation is being continiued on A2 block. Project Twin Tower is a big responsibility and prestige for our company. I want to thank each employee of ICE for the works they've done. We'll continue installation of elevators with the same success in every block"- says Giorgi Bakhtadze director of the company.

ICE will install 28 units of Shanghai Mitsubishi elevators on Twin Tower project. Orbi Twin Tower is a huge project with 4500 rooms being built in Batumi.

Share
Installed rails and counterweight in the shaft installed motors in machine room 7 elevators have been installed at Twin Tower project